* Location: Al Zour   
 
* Location: Al Zour   
 
* Capacity: 11 million tons/annum  
 
* Capacity: 11 million tons/annum  
* Status: Under Construction
+
* Status: In operation
 
 
  
 
=== Brief Description ===
 
=== Brief Description ===
Line 21: Line 20:
  
 
=== Ongoing Projects/Project Status ===
 
=== Ongoing Projects/Project Status ===
* Commissioning is expected in [[LNG Terminal Projects Completed in 2021 | 2021]]
+
* The project was commissioned in [[LNG Terminal Projects Completed in 2021 | 2021]]
 
 
  
 
=== Suppliers / Customers ===
 
=== Suppliers / Customers ===

Latest revision as of 14:17, 6 January 2022

Summary Information

  • Ownership: Kuwait Petroleum Corporation
  • Website: https://www.kpc.com.kw/
  • Location: Al Zour
  • Capacity: 11 million tons/annum
  • Status: In operation

Brief Description

  • A large scale import terminal including a regasification system, eight LNG storage tanks with a capacity of 225,500 m³ each, two marine jetties, and berthing facilities for loading.


Technical Details

  • Storage capacity: 1.8 BCM
  • Unloading capacity:
  • Send out capacity:
  • Constructor: Hyundai E&C and Hyundai Engineering


Ongoing Projects/Project Status

  • The project was commissioned in 2021

Suppliers / Customers

  • Suppliers:
  • Customers:


History

  • 2016 - EPC contract awarded
  • 2018 - Korea Eximbank signs financing deal
  • 2021 - Terminal operation starts

Other Information

  • -

Links

  1. https://kipic.com.kw/SUMM_LNGI_R01_25032018.pdf Environmental Impact Assessment
  2. Hyundai E&C and Hyundai Engineering win the Al-Zour LNG Import Terminal Project in Kuwait
  3. Korea Eximbank to Provide USD 1.15 Billion for LNG Import Terminal Project in Kuwait