Difference between revisions of "Ionian Adriatic Pipeline (IAP)"

From A Barrel Full
Jump to navigation Jump to search
 
Line 15: Line 15:
 
* The construction of the IAP, over 500 km long, will provide a sustainable, diversified and reliable supply of natural gas for Albania, Montenegro, southern Croatia, and Bosnia and Herzegovina.
 
* The construction of the IAP, over 500 km long, will provide a sustainable, diversified and reliable supply of natural gas for Albania, Montenegro, southern Croatia, and Bosnia and Herzegovina.
 
* Its 5 bcm/y capacity provides the natural gas supply of Albania (1 bcm), Montenegro (0.5 bcm), the south of Bosnia and Herzegovina (1 bcm) and Croatia (2.5 bcm)
 
* Its 5 bcm/y capacity provides the natural gas supply of Albania (1 bcm), Montenegro (0.5 bcm), the south of Bosnia and Herzegovina (1 bcm) and Croatia (2.5 bcm)
 +
** On the territory of Croatia the construction of four sections and a compressor station in Dugopolje has been planned. The mentioned sections are: Split – Zagvozd (52 km), Zagvozd – Ploče (50 km), Ploče – Dubrovnik (103 km) and Dubrovnik – Prevlaka – Dobreč (MN) in the length of 47 km.
  
 
=== History ===
 
=== History ===
Line 25: Line 26:
 
# [https://wbif.eu/project/PRJ-MULTI-ENE-003 WBIF Project page]
 
# [https://wbif.eu/project/PRJ-MULTI-ENE-003 WBIF Project page]
 
# [https://www.energy-community.org/regionalinitiatives/infrastructure/PLIMA/Gas16.html Energy Community, webpage]
 
# [https://www.energy-community.org/regionalinitiatives/infrastructure/PLIMA/Gas16.html Energy Community, webpage]
 +
# [https://www.plinacro.hr/default.aspx?id=1228 Project information from Plinacro]
  
 
[[category:Pipeline]]
 
[[category:Pipeline]]
[[category:Country]]
+
[[category:Croatia]]
[[category:Company]]
 

Latest revision as of 09:18, 23 January 2023

Summary Information

  • Source: Split, Croatia
  • Destination: Fieri, Albania
  • Ownership:
  • Website:
  • Length: 500 kilometres ( miles)
  • Capacity: 5 BCM per year
  • Status: /Planned

Details

  • The Ionian Adriatic Pipeline (IAP) connects the existing and planned gas transmission system of Croatia with the Trans-Adriatic Pipeline TAP
  • The IAP will have a bidirectional gas flow and it will be fully compatible with the Hrvatska LNG Terminal on the island of Krk
  • The project aims to establish a new supply route for natural gas from the Middle East and Caspian region along the Adriatic coast.
  • The construction of the IAP, over 500 km long, will provide a sustainable, diversified and reliable supply of natural gas for Albania, Montenegro, southern Croatia, and Bosnia and Herzegovina.
  • Its 5 bcm/y capacity provides the natural gas supply of Albania (1 bcm), Montenegro (0.5 bcm), the south of Bosnia and Herzegovina (1 bcm) and Croatia (2.5 bcm)
    • On the territory of Croatia the construction of four sections and a compressor station in Dugopolje has been planned. The mentioned sections are: Split – Zagvozd (52 km), Zagvozd – Ploče (50 km), Ploče – Dubrovnik (103 km) and Dubrovnik – Prevlaka – Dobreč (MN) in the length of 47 km.

History

  • 2014 - Feasibility Study financed by the WBIF was completed

Other Information

  • -

Links

  1. WBIF Project page
  2. Energy Community, webpage