Difference between revisions of "Plaquemines LNG Export Terminal Project"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
Line 8: | Line 8: | ||
=== Brief Description === | === Brief Description === | ||
− | * - | + | * The terminal will have up to thirty-six 0.626 MTPA liquefaction trains, configured in eighteen blocks, with up to six pre-treatment trains |
+ | * There will be up to three ship loading berths for LNG vessels carrying a capacity of up to 185,000 cubic meters and up to four 200,000 cubic meter full containment LNG storage tanks | ||
+ | * Two 720 MW combined cycle gas turbine power plants, including additional 25 MW gas-fired aeroderivative turbines | ||
+ | * A utility dock on the Mississippi River to handle waterborne deliveries of equipment and material during both construction and project operations. | ||
+ | * Gas will be supplied by two 42-inch diameter pipelines, 15 and 12 miles long respectively, that connect to existing interstate natural gas pipelines. | ||
=== Technical Details === | === Technical Details === |
Revision as of 15:16, 20 December 2021
Contents
Summary Information
- Ownership: Venture Global
- Website: http://venturegloballng.com/
- Location:
- Capacity: million tons/annum
- Status: (In Operation / Planned / Under Construction)
Brief Description
- The terminal will have up to thirty-six 0.626 MTPA liquefaction trains, configured in eighteen blocks, with up to six pre-treatment trains
- There will be up to three ship loading berths for LNG vessels carrying a capacity of up to 185,000 cubic meters and up to four 200,000 cubic meter full containment LNG storage tanks
- Two 720 MW combined cycle gas turbine power plants, including additional 25 MW gas-fired aeroderivative turbines
- A utility dock on the Mississippi River to handle waterborne deliveries of equipment and material during both construction and project operations.
- Gas will be supplied by two 42-inch diameter pipelines, 15 and 12 miles long respectively, that connect to existing interstate natural gas pipelines.
Technical Details
- Storage capacity:
- Constructor:
- Licensor:
Ongoing Projects/Project Status
- Commissioning is expected in 2024
Suppliers / Customers
- Suppliers:
- Customers:
History
- 2018 - PGNIG signed a contract for 2.5 million tons per annum
- 2021 - PGNIG increased their contract to 4.0 million tons per annum