* Nelson Complexity: | * Nelson Complexity: | ||
* Project Stage: Engineering | * Project Stage: Engineering | ||
− | * Expected Completion: Commissioning is expected in | + | * Expected Completion: Commissioning is expected in 2028 |
* Budget: | * Budget: | ||
=== The Project === | === The Project === | ||
Line 13: | Line 13: | ||
* Project Summary: The refinery will be a medium to large sized plant, with high complexity. | * Project Summary: The refinery will be a medium to large sized plant, with high complexity. | ||
* Main Contractors: | * Main Contractors: | ||
− | ** KBR: FEED | + | ** KBR: FEED and PMC |
** KBR: License and engineering services for grassroots FCC and Hydroprocessing technologies | ** KBR: License and engineering services for grassroots FCC and Hydroprocessing technologies | ||
** Engineers India Limited (EIL): FEED Revalidation, Licensor Selection and BDEP Review | ** Engineers India Limited (EIL): FEED Revalidation, Licensor Selection and BDEP Review | ||
Line 37: | Line 37: | ||
* 2013 - Sonangol chooses Standard Chartered Bank for financial consulting | * 2013 - Sonangol chooses Standard Chartered Bank for financial consulting | ||
* 2014 - Sonangol and China Development Bank signed financing agreement | * 2014 - Sonangol and China Development Bank signed financing agreement | ||
− | * 2016 | + | * 2016 - Engineers India awarded FEED revalidation contract |
+ | * 2024 - KBR awarded project management contract | ||
+ | |||
=== Other Information === | === Other Information === | ||
− | * | + | * The project has been postponed and delayed a number of times. |
=== Links === | === Links === | ||
Line 50: | Line 52: | ||
# [http://killajoules.wikidot.com/blog:5653 Sonangol and China Development Bank signed important financing agreement] | # [http://killajoules.wikidot.com/blog:5653 Sonangol and China Development Bank signed important financing agreement] | ||
# [http://killajoules.wikidot.com/archive:sonangol-awards-services-for-lobito-refinery-project Sonangol awards Services for Lobito Refinery Project to EIL] | # [http://killajoules.wikidot.com/archive:sonangol-awards-services-for-lobito-refinery-project Sonangol awards Services for Lobito Refinery Project to EIL] | ||
+ | # [https://refiningnews.blogspot.com/2024/03/kbr-awarded-project-management-contract.html KBR Awarded Project Management Contract for Sonangol’s New Lobito Refinery Project] | ||
[[Category:Refinery]] | [[Category:Refinery]] | ||
[[Category:Angola]] | [[Category:Angola]] | ||
[[Category:Sonangol]] | [[Category:Sonangol]] |
Latest revision as of 16:29, 14 March 2024
Contents
Summary Information
- Ownership: Sonangol
- Website: http://www.sonangol.co.ao/
- Wiki Page: Lobito Refinery
- Location: About 8 km north of Lobito, Benguela, Angola
- Capacity: 10.0 million tons/annum & 200,000 bbl/day
- Nelson Complexity:
- Project Stage: Engineering
- Expected Completion: Commissioning is expected in 2028
- Budget:
The Project
- Project Type: Greenfield
- Project Summary: The refinery will be a medium to large sized plant, with high complexity.
- Main Contractors:
- KBR: FEED and PMC
- KBR: License and engineering services for grassroots FCC and Hydroprocessing technologies
- Engineers India Limited (EIL): FEED Revalidation, Licensor Selection and BDEP Review
Refining Units
- Atmospheric Distillation
- Vacuum Distillation
- FCC
- Hydrocracker
- Diesel Hydrotreating (DHT)
- Kerosene Hydrotreating (KHT)
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
- The refinery will process acid Angolan crudes (high percentage of TAN) and heavy crudes such as Kuito Crude and Dalia Crude
Products Produced
- Unleaded gasoline, diesel, jet fuel (Jet1), illuminant oil, LPG and limited quantities of sulfur and petrocoke.
- The specifications of the products processed will match those of the export target markets which include Europe and the USA.
History
- 2007 - Sinopec drops out of project
- 2008 - KBR awarded FEED contract
- 2009 - KBR wins unit licence contracts
- 2013 - Sonangol chooses Standard Chartered Bank for financial consulting
- 2014 - Sonangol and China Development Bank signed financing agreement
- 2016 - Engineers India awarded FEED revalidation contract
- 2024 - KBR awarded project management contract
Other Information
- The project has been postponed and delayed a number of times.
Links
- Project Information from Sonangol
- Sonaref Project, Downstream Today
- Sicim Pipeline References
- KBR Awarded Lobito Refinery FEED Contract by Sonangol, E.P.
- KBR Awarded FCC and Hydroprocessing Technology Contract for Sonangol, E.P. Refinery
- Construction project Lobito Refinery: Hiring Financial Advisor
- Sonangol and China Development Bank signed important financing agreement
- Sonangol awards Services for Lobito Refinery Project to EIL
- KBR Awarded Project Management Contract for Sonangol’s New Lobito Refinery Project