* Location: Teluk Bintuni, Papua Barat province | * Location: Teluk Bintuni, Papua Barat province | ||
* Capacity: 3.8 million tons/annum | * Capacity: 3.8 million tons/annum | ||
− | * Status: | + | * Status: In operation |
=== Brief Description === | === Brief Description === | ||
Line 30: | Line 30: | ||
* 2014 - Project receives AMDAL approval and environmental permit | * 2014 - Project receives AMDAL approval and environmental permit | ||
* 2016 - Final investment decision taken | * 2016 - Final investment decision taken | ||
− | * | + | * 2016 - EPC contract awarded to Chiyoda |
+ | * 2023 - First cargo loaded | ||
=== Other Information === | === Other Information === | ||
Line 41: | Line 42: | ||
# [https://abarrelfull.blogspot.com/2021/11/chiyoda-awarded-epc-contract-for.html Chiyoda Awarded EPC Contract for Tangguh Expansion Project in Indonesia] | # [https://abarrelfull.blogspot.com/2021/11/chiyoda-awarded-epc-contract-for.html Chiyoda Awarded EPC Contract for Tangguh Expansion Project in Indonesia] | ||
# [https://abarrelfull.blogspot.com/2021/11/tangguh-enters-into-financing.html Tangguh Enters into Financing agreements for the Train 3 Project] | # [https://abarrelfull.blogspot.com/2021/11/tangguh-enters-into-financing.html Tangguh Enters into Financing agreements for the Train 3 Project] | ||
+ | # [https://lng-news.blogspot.com/2023/10/bp-ships-first-cargo-from-indonesias.html bp ships first cargo from Indonesia’s expanded Tangguh LNG facility] | ||
+ | |||
+ | [[category:LNG]] | ||
+ | [[category:Indonesia]] | ||
+ | [[category:BP]] |
Latest revision as of 09:43, 19 October 2023
Contents
Summary Information
- Ownership: BP
- Website: http://www.bp.com/
- Location: Teluk Bintuni, Papua Barat province
- Capacity: 3.8 million tons/annum
- Status: In operation
Brief Description
- The project is the third train of the existing Tangguh LNG Terminal
- The Tangguh Expansion Project will add a third LNG process train (Train 3) and 3.8 million tons per annum (mtpa) of production capacity to the existing facility, bringing total plant capacity to 11.4 mtpa.
- The project also includes two offshore platforms, 13 new production wells, an expanded LNG loading facility, and supporting infrastructure.
Technical Details
- Storage capacity:
- Constructor: Chiyoda was the EPC contractor
- Licensor:
Ongoing Projects/Project Status
- Commissioning is expected in 2022
Suppliers / Customers
- Suppliers: Gas fields in the Berau and Bintuni bay area including the Massive Tangguh Gas Field
- Customers:
- 75% of the Train 3 annual LNG production is sold to the Indonesian state electricity company PT. PLN (Persero)
- The remaining volumes are under contract to Kansai Electric Power Company in Japan, the other foundation buyer for Train 3.
History
- 2012 - Bpmigas announces support for the project
- 2014 - Project receives AMDAL approval and environmental permit
- 2016 - Final investment decision taken
- 2016 - EPC contract awarded to Chiyoda
- 2023 - First cargo loaded
Other Information
- -
Links
- Bpmigas Is Ready To Approve POFD Of Tangguh Train-3
- Tangguh Expansion Project receives AMDAL approval and environmental permit
- Announcement of Final Investment Decision to Expand Indonesia’s Tangguh LNG Facility
- Chiyoda Awarded EPC Contract for Tangguh Expansion Project in Indonesia
- Tangguh Enters into Financing agreements for the Train 3 Project
- bp ships first cargo from Indonesia’s expanded Tangguh LNG facility