* The Morecambe Hub comprises three fields in the East Irish Sea - North Morecambe, South Morecambe and Rhyl. The fields lie approximately 25km south west of Walney Island, across blocks 110/2a, 110/3a, 110/8a and 113/27b, in water depths that range from 17 to 35m. | * The Morecambe Hub comprises three fields in the East Irish Sea - North Morecambe, South Morecambe and Rhyl. The fields lie approximately 25km south west of Walney Island, across blocks 110/2a, 110/3a, 110/8a and 113/27b, in water depths that range from 17 to 35m. | ||
+ | * The '''South Morecambe gas field''' is one of the UK’s largest fields | ||
+ | * The **Central Processing Complex** is a three-platform, bridge-linked complex with a flare boom tower | ||
+ | ** In the centre of the complex is the Central Production Platform (CPP). | ||
+ | ** The import pipelines from the four satellite platforms terminate here, and the gas/condensate export pipeline begins at the CPP | ||
+ | ** Located at the western end of the complex, AP1 is the accommodation platform | ||
+ | ** At the eastern end of the complex, DP1 is the Drilling platform. | ||
+ | ** In addition, production units DP3, DP4, DP6 and DP8 are also connected | ||
+ | ** It has risers from eight wells, plus a flexible import riser and control umbilical to Bains | ||
+ | * Gas is exported to the [[Rampside Gas Terminal]] | ||
+ | * The '''North Morecambe gas field''' consists of a single normally unmanned small steel platform | ||
+ | * The Rivers, [[Millom and Dalton Gas Fields]], operated by ConocoPhillips, are tied back to the normally-unmanned North Morecambe platform. | ||
+ | * Gas from the '''Rhyl Gas Field''' is also transported via the North Morecambe platform | ||
=== Contractors === | === Contractors === | ||
+ | * '''South Morecombe''' | ||
+ | * **Haverton Hill:** Construction of Morecambe platform modules | ||
+ | * **Heerema Marine Contractors:** Installation of CPP, DP3, DP4, DP6 & DP8 | ||
+ | * **FoundOcean:** Grouting for CPP, DP1, DP3, DP4, DP6, DP8, AP1 and Flare Tower | ||
* '''North Morecombe''' | * '''North Morecombe''' | ||
* **Heerema Marine Contractors:** North Morecambe platform | * **Heerema Marine Contractors:** North Morecambe platform | ||
Line 20: | Line 36: | ||
=== History === | === History === | ||
+ | * 1974 - South Morecambe Gas Field discovered | ||
* 1976 - North Morecambe Gas Field discovered | * 1976 - North Morecambe Gas Field discovered | ||
− | * 1992 - Government approval granted | + | * 1982 - Government approval granted for South Morecambe |
+ | * 1985 - First gas produced from South Morecambe | ||
+ | * 1989 - DP6 and DP8 platforms installed | ||
+ | * 1992 - Government approval granted for North Morecombe | ||
* 1994 - First gas produced from North Morecombe | * 1994 - First gas produced from North Morecombe | ||
* 2013 - First gas from Rhyl | * 2013 - First gas from Rhyl | ||
+ | * 2017 - Spirit energy becomes the operator | ||
=== Geology === | === Geology === |
Revision as of 16:45, 24 August 2023
Summary Information
- Operator: Spirit Energy
- Country: UK
- Location: East Irish Sea
- Production start:
- Partners:
- Type: Gas
- Estimated Reserves:
- Production Volume:
Description
- The Morecambe Hub comprises three fields in the East Irish Sea - North Morecambe, South Morecambe and Rhyl. The fields lie approximately 25km south west of Walney Island, across blocks 110/2a, 110/3a, 110/8a and 113/27b, in water depths that range from 17 to 35m.
- The South Morecambe gas field is one of the UK’s largest fields
- The **Central Processing Complex** is a three-platform, bridge-linked complex with a flare boom tower
- In the centre of the complex is the Central Production Platform (CPP).
- The import pipelines from the four satellite platforms terminate here, and the gas/condensate export pipeline begins at the CPP
- Located at the western end of the complex, AP1 is the accommodation platform
- At the eastern end of the complex, DP1 is the Drilling platform.
- In addition, production units DP3, DP4, DP6 and DP8 are also connected
- It has risers from eight wells, plus a flexible import riser and control umbilical to Bains
- Gas is exported to the Rampside Gas Terminal
- The North Morecambe gas field consists of a single normally unmanned small steel platform
- The Rivers, Millom and Dalton Gas Fields, operated by ConocoPhillips, are tied back to the normally-unmanned North Morecambe platform.
- Gas from the Rhyl Gas Field is also transported via the North Morecambe platform
Contractors
- South Morecombe
- **Haverton Hill:** Construction of Morecambe platform modules
- **Heerema Marine Contractors:** Installation of CPP, DP3, DP4, DP6 & DP8
- **FoundOcean:** Grouting for CPP, DP1, DP3, DP4, DP6, DP8, AP1 and Flare Tower
- North Morecombe
- **Heerema Marine Contractors:** North Morecambe platform
- **McDermott-ETPM:** Subsea installations
- **Subsea 7:** DPPA Platform
- **FoundOcean:** Grouting for DPPA Platform
History
- 1974 - South Morecambe Gas Field discovered
- 1976 - North Morecambe Gas Field discovered
- 1982 - Government approval granted for South Morecambe
- 1985 - First gas produced from South Morecambe
- 1989 - DP6 and DP8 platforms installed
- 1992 - Government approval granted for North Morecombe
- 1994 - First gas produced from North Morecombe
- 2013 - First gas from Rhyl
- 2017 - Spirit energy becomes the operator
Geology
Links
- UK Oil and Gas Fields by Approval Date
- List Of Oil and Gas Production Platforms In The UK
- FoundOcean Subsea References
- Serimax Pipeline References
- Centrica Energy delivers first production from Rhyl gas field
- Spirit Energy launched following completion of Centrica and Bayerngas Norge E&P joint venture