− | * - | + | * Aker Solutions |
+ | ** Front-end engineering and design work (FEED) | ||
+ | ** Engineering, procurement, construction, and installation (EPCI) of the complete wellhead platform, consisting of a topside and a steel jacket, as well as related load-out and offshore hook-up and commissioning. | ||
=== History === | === History === | ||
− | * | + | * 2016 - Shell acquired BG Group, which previously owned the field |
+ | * 2019 - FEED awarded | ||
* 2022 - Final investment decision | * 2022 - Final investment decision | ||
Line 26: | Line 29: | ||
=== Links === | === Links === | ||
# [https://abarrelfull.blogspot.com/2023/03/shell-invests-in-jackdaw-gas-field-in.html Shell invests in the Jackdaw gas field in the UK North Sea] | # [https://abarrelfull.blogspot.com/2023/03/shell-invests-in-jackdaw-gas-field-in.html Shell invests in the Jackdaw gas field in the UK North Sea] | ||
+ | # [https://abarrelfull.blogspot.com/2023/03/aker-solutions-asa-aker-solutions.html Aker Solutions ASA: Aker Solutions Awarded EPCI Contract for the Jackdaw Platform from Shell] | ||
Revision as of 15:32, 21 March 2023
Summary Information
- Operator: Shell
- Country: United Kingdom
- Location:
- Production start:
- Partners:
- Type: Gas
- Estimated Reserves:
- Production Volume:
Description
- The Jackdaw field is located approximately 250 km east of Aberdeen, Scotland, and is adjacent to the UK/Norway median line.
- The Jackdaw development consists of a new Wellhead Platform (WHP), four production wells and a 31 km pipeline from the Jackdaw WHP to the Shearwater gas hub.
- Peak production from the field is estimated at 40,000 barrels of oil equivalent per day.
Contractors
- Aker Solutions
- Front-end engineering and design work (FEED)
- Engineering, procurement, construction, and installation (EPCI) of the complete wellhead platform, consisting of a topside and a steel jacket, as well as related load-out and offshore hook-up and commissioning.
History
- 2016 - Shell acquired BG Group, which previously owned the field
- 2019 - FEED awarded
- 2022 - Final investment decision