=== Brief Description === | === Brief Description === | ||
* The project is the third train of the existing [[Tangguh LNG Terminal]] | * The project is the third train of the existing [[Tangguh LNG Terminal]] | ||
− | * The | + | * The Tangguh Expansion Project will add a third LNG process train (Train 3) and 3.8 million tons per annum (mtpa) of production capacity to the existing facility, bringing total plant capacity to 11.4 mtpa. |
− | + | * The project also includes two offshore platforms, 13 new production wells, an expanded LNG loading facility, and supporting infrastructure. | |
=== Technical Details === | === Technical Details === |
Revision as of 09:00, 19 November 2021
Contents
Summary Information
- Ownership: BP
- Website: http://www.bp.com/
- Location: Teluk Bintuni, Papua Barat province
- Capacity: 3.8 million tons/annum
- Status: Under construction
Brief Description
- The project is the third train of the existing Tangguh LNG Terminal
- The Tangguh Expansion Project will add a third LNG process train (Train 3) and 3.8 million tons per annum (mtpa) of production capacity to the existing facility, bringing total plant capacity to 11.4 mtpa.
- The project also includes two offshore platforms, 13 new production wells, an expanded LNG loading facility, and supporting infrastructure.
Technical Details
- Storage capacity:
- Constructor: Chiyoda was the EPC contractor
- Licensor:
Ongoing Projects/Project Status
- Commissioning is expected in 2022
Suppliers / Customers
- Suppliers:
- Customers:
- 75% of the Train 3 annual LNG production is sold to the Indonesian state electricity company PT. PLN (Persero)
- The remaining volumes are under contract to Kansai Electric Power Company in Japan, the other foundation buyer for Train 3.
History
- 2012 - Bpmigas announces support for the project
- 2014 - Project receives AMDAL approval and environmental permit
- 2016 - Final investment decision taken
- 2106 - EPC contract awarde to Chiyoda
Other Information
- -