Yanos Yaroslavl Refinery Upgrading Project
Jump to navigation
Jump to search
Contents
Summary Information
- Ownership: Slavneft
- Website: http://www.slavneft.ru/
- Wiki Page: Yanos Yaroslavl Refinery
- Location: Yaroslavl
- Capacity: 14 million tons/annum & 280,000 bbl/day
- Nelson Complexity:
- Project Stage: Completed 2012
- Budget:
The Project
- Project Type: Major Upgrade
- Project Summary: The large-scale Upgrading Program has being implemented at YaNOS for more than 10 years. During 2002 – 2010 Slavneft invested over 1.5 bln USD in the Refinery’s development. Over this period 17 large production facilities, including the Deep Oil Processing Plant, were constructed and revamped at the Subsidiary. The Deep Oil Processing Plant consists of the Hydrocracking, Visbreaking and Catalytic Reforming Units.
- Main Contractors
Refining Units
- Hydrocracking
- Visbreaking
- Catalytic Reforming Units
- Isomerization Unit
- Cat-Cracked Gasoline Hydrotreatment Unit
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
-
Products Produced
- The upgrade reduces the yield of heavier products, enables the production of high octane gasoline and cleaner products meeting Euro V specifications
History
- 2011 - Isomerisation Unit Commissioned
- 2011 - Catalytic Cracking Gasoline Hydrotreatment Unit Commissioned
- 2012 - Project completed