Tamil Nadu Refinery Project

From A Barrel Full
Jump to navigation Jump to search

+++ Summary Information

  • Ownership: Nagarjuna Oil Corporation Limited
  • Website: http://www.nocl.co.in/
  • Wiki Page: [[[Cuddalore Tamil Nadu Refinery]]]
  • Location: Cuddalore, Tamil Nadu, India
  • Capacity: 6,0 million tons/annum & 120,000 bbl/day
  • Nelson Complexity: 8.74
  • Project Stage:
  • Expected Completion: [[[Refinery Projects to be Completed in 2012 | 2012]]]
  • Budget:

+++ The Project

  • Project Type: Relocation of an existing refinery from Germany
  • Project Summary:
  • Main Contractors:
* Punj Lloyd setting up of Crude and Vacuum Distillation units, Gasoline and saturated gas plant and Catalytic Hydro-De Sulphurization and Isomerization Units.

+++ Refining Units

  • Atmospheric Distillation
  • Vacuum Distillation unit
  • Catalytic Hydro-De Sulphurization
  • Isomerization Unit
  • Methyl Tertiary Butyl Ether Unit
  • Fluid Catalytic Cracking Unit
  • Delayed Coker Unit
  • Diesel Hydrodesulphurization Unit

+++ Terminal Capacity

  • Crude Oil:
  • Refined Products:

+++ Crude Supply

  • The Crudes that are to be processed in the refinery are [[[Bonny Light Crude Oil]]] and Arab Mix crude


+++ Products Produced

  • The refinery will produce auto fuels that will meet Indian and international specifications (Euro III & Euro IV)

+++ History

  • 2006 - Site preparation began
  • 2010 - Punj Lloyd awarded assembly contract
  • 2012 - Trafigura invests USD250M to acquire 24% of the project

+++ Other Information

  • The refinery is Mobil's former [[[Woerth refinery]]] from Germany, which was closed down in 1995


+++ Relevant Links