Rijeka Refinery Delayed Coker Project

From A Barrel Full
Jump to navigation Jump to search

Summary Information

  • Ownership: INA (MOL)
  • Website: http://www.ina.hr/
  • Wiki Page: Rijeka Refinery
  • Location: Rijeka, Croatia
  • Capacity: million tons/annum & bbl/day
  • Nelson Complexity:
  • Project Stage: Under construction
  • Expected Completion: 2023
  • Budget: EUR 450 million

The Project

  • Project Type: Upgrade
  • Project Summary:
    • The Project includes the debottlenecking of existing units and construction of new ones
    • The delayed coker involves construction of the unit itself as well as solutions for coke storage and sea jetty construction
  • Main Contractors:
    • Kinetics Technology: EPC contract on a Lump Sum Turnkey basis
    • engineering, procurement of all equipment and materials, construction and erection work for a new Delayed Coking Unit with coke handling and ship loading, Sour Water Stripper, Amine Recovery units and the revamping of Hydrocracker, Sulphur Recovery, and Utilities & Offsites units.
  • Licences:
    • Bechtel: Licence for Delayed coking unit

Refining Units

  • Delayed Coker
  • Sour Water Stripper
  • Amine Recovery units
  • Hydrocracker, Sulphur Recovery (Revamping)

Terminal Capacity

  • Crude Oil:
  • Refined Products:

Crude Supply

  • -

Products Produced

  • The refinery will no longer produce residual fuel oil

History

  • 2014 - Bechtel technology chosen for Coker
  • 2019 - Kinetics Technology awarded EPC contract

Other Information

  • The project was significantly delayed due to political problems between MOL, the main shareholder and the Croatian government


Links

  1. Kinetics Technology Refinery References
  2. Bechtel's ThruPlus® Coking Technology Selected for Croatian Refinery
  3. Maire Tecnimont Awarded A €450 Mn Refining Project In Croatia